| Fürstenfeld | ||||
| Artifical turf (Football turf) in Jugend- & Familiengästehaus (youth and family hostel) in Fürstenfeld / Styria | ||||
| Use | ||||
| Football for professional, students, amateurs and youth Intensity of use: up to 1,000 hours per year |
||||
| Range of services | ||||
| Concept, technical planning, design (with underfloor sprinkling and flood-lighting), management of tendering process, technical supervision and overall management. | ||||
| Project data | ||||
| Artifical turf pitch (Football turf), A = 6.784 m2 (60 x 100 m) installed on an elastic shokpad (in-situ applied), infill of quartz sand and SBR granulate. The ground was extremely soft, wherefore it had to be subject to soil stabilisation |
||||
| Project costs | ||||
| EUR 649.000,-- (excluding VAT) | ||||
| Planning and design phase | ||||
| 01/2009 - 05/2009 | ||||
| Construction phase | ||||
| 05/2009 - 07/2010 | ||||